How long does a shopfront installation take?
A standard aluminium shopfront takes 3 to 4 weeks to make after drawing sign-off and 1 or 2 days to fit. A shutter on its own takes 2 to 3 weeks after survey. The time on site is short. Most of the programme sits in the stages before anything is made.
Count from the day you sign off the drawing, not the day you first call. Before that point the pace depends on the survey date, your answers and any consents.
What happens week by week?
Here is how a combined aluminium frontage and shutter runs once the drawing is agreed. Week 0 is the day you accept the quotation and sign off the drawing.
| Week | What happens | Who does it |
|---|---|---|
| Before week 0 | Survey, itemised quotation and drawing | Us, with your comments |
| Before week 0, if needed | Planning, listed building consent and landlord consent | As agreed on your quotation |
| Week 0 | You accept, pay the deposit and sign off the drawing | You |
| Weeks 1 to 4 | Frame and shutter made to the survey | Us |
| Week 3 or 4 | We confirm the fitting date | Us and you |
| Week 4 or 5 | Old frontage out, new frontage and shutter in, over 1 or 2 days | Our team or subcontract installers |
| Handover | Test, keys, remotes and a note of the manual override | Us |
This is a typical pattern and not a promise. A frontage in another material or a larger job takes longer, and your quotation gives the lead time for your job.
How long do the survey and drawing stages take?
That depends mostly on when we can meet on site and how quickly you can reply. At survey we measure the structural opening and check the lintel, the guide fixings and the floor level. We then send an itemised quotation and a drawing showing how the box, guides and glass fit together.
The survey and quotation for new work are free. Allow time to read the drawing properly, because changes are easy on paper and expensive after the order goes in. Show it to your landlord and your sign maker at this stage. Nothing is ordered until you accept the quotation.
When does planning permission fit in?
Planning comes first, and it adds time. An external shutter or a changed frontage usually needs permission, because shops have no permitted development right for this work. Do not order until you have the decision.
The timetable belongs to the council, so ask the planning department what to expect when you apply. Our planning pages show who to contact. If the building is listed, allow more time, because consent is a separate process. See our guide to heritage shopfronts.
Your quotation is valid for 90 days. If the decision will run past that, tell us and we will check the quotation before you accept.
How long does each product take to make?
It takes from 2 to 6 weeks, depending on the product. These are our current lead times.
| Product | Lead time |
|---|---|
| Shopfront and shutter package | 3 to 4 weeks after drawing sign-off |
| Aluminium shopfront | 3 to 4 weeks after drawing sign-off |
| Frameless glass shopfront | 4 to 5 weeks after drawing sign-off |
| Bi-folding shopfront | 4 to 5 weeks after drawing sign-off |
| Steel shopfront | 5 to 6 weeks after drawing sign-off |
| Manual, electric, perforated or insulated shutter | 2 to 3 weeks after survey |
| Security grille | 2 to 3 weeks after survey |
| Fire-rated shutter | 4 to 6 weeks after survey |
How long will my shop be closed?
A standard opening takes 1 or 2 days to fit, and you may be able to trade around part of that. The old frontage has to come out and the new one go in, so we plan it to keep the shop secure each night. If the job cannot be finished in a day, we agree with you how the frontage will be left overnight.
Tell us your quietest days at survey. We plan around them where we can. A city street with a tight loading window, or a job needing a scaffold or lift, takes more planning.
What can hold up a shopfront project?
Consents and changes hold up most projects. Watch for these:
- A planning decision that takes longer than hoped, or comes with conditions.
- Landlord consent that nobody asked for until late.
- Changes to the drawing after sign-off.
- A building control application for the frame and glass, as replacing a whole unit is building work.
- Structural surprises, such as a lintel or stallriser that needs work once the old frontage is out.
- Sign consent left until the end. See our guide to shop signs.
Most of these can be spotted at survey, which is why we ask about them early.
When do I pay?
You pay in 3 stages, as set out on the quotation: a deposit on acceptance, a stage payment on the first day of installation, and the balance on satisfactory completion. As a guide, an aluminium frontage with a hidden electric shutter on a 3.0 x 2.6 m opening costs £5,514 to £6,954 inc VAT (£4,595 to £5,795 plus VAT). Work out a guide price or read our guide to shopfront costs.
Common questions
Can you fit a shopfront faster?
Lead times are set by manufacture, so we cannot promise a shorter date. Tell us if you have a fixed opening date, and we will say honestly whether it can be met.
Can I trade during the work?
Often for part of it, depending on the job. A standard opening takes 1 or 2 days to fit, and we plan around your quietest days where we can.
When does the lead time start?
For frontages it starts at drawing sign-off. For shutters on their own it starts after survey. Nothing is ordered until you accept the quotation.
Does planning have to be finished first?
If planning permission is needed, yes. Get the decision before you order, because a refusal or a condition can change what gets made.
How long does replacement glass take?
Glass is made in 3 to 7 days. Broken glass is a repair job, so it follows a different and shorter path than a new frontage.
Sources
Related services

Shopfront and shutter packages
A new frontage and its shutter, designed and fitted as one job.
from £4,074 inc VAT
Aluminium shopfronts
Powder-coated frontages, made to the measured opening.
from £2,940 inc VAT
Electric roller shutters
Motorised shutters with key switch or remote control.
from £1,740 inc VAT